Venice Payment Plan at DAMAC Lagoons

Venice launch payment plan from the DAMAC sheet. 20 percent deposit, calendar and build milestone instalments, then 20 percent due on completion.

This was the launch payment plan for a cluster that is now sold out and still in construction. Resale purchases do not follow it.

PropertyMonitor recorded Venice as 15 percent deposit, 55 percent during construction and 30 percent on handover, matching Portofino. The DAMAC Venice payment plan PDF instead shows 20 percent deposit, 60 percent during construction and 20 percent on completion, with four calendar instalments and four build milestone instalments. This page uses the DAMAC sheet, which outranks the registry free text for payment schedules.

20 percent deposit, 60 percent across construction and 20 percent on completion.

Only 20 percent of the Venice price is tied to calendar dates, across four instalments running to 12 months. Another 40 percent is tied to verified build milestones at 40, 50, 60 and 70 percent completion. Twenty percent remains due on completion. By comparison, Costa Brava and Nice leave 50 percent to handover on a purely calendar construction schedule, Portofino leaves 30 percent to handover, and Morocco, Ibiza, Monte Carlo and Malta leave 20 percent to handover.

There is no post handover plan. 4 percent DLD is payable in addition to the initial deposit.

Venice launch payment plan. Source: DAMAC Venice Payment Plan.pdf. 10 rows. Headline 20 / 60 / 20. Percentages sum to 100.
MilestoneWhenTriggerValue
DepositImmediatecalendar20%
1st instalmentWithin 3 months of salecalendar5%
2nd instalmentWithin 6 months of salecalendar5%
3rd instalmentWithin 9 months of salecalendar5%
4th instalmentWithin 12 months of salecalendar5%
5th instalmentOn 40 percent project completionbuild milestone10%
6th instalmentOn 50 percent project completionbuild milestone10%
7th instalmentOn 60 percent project completionbuild milestone10%
8th instalmentOn 70 percent project completionbuild milestone10%
9th instalmentOn completioncompletion20%
Total100%

Our reading of two sourced figures: On the reported 74.43 percent progress, every milestone instalment through the 70 percent trigger has fallen due and the completion instalment has not.

Handover share across clusters

Corrected handover comparison from sourced payment plans on this site. Venice uses the DAMAC sheet figure of 20 percent on completion.
ClustersHandover share
Costa Brava and Nice50 percent at handover
Portofino30 percent at handover
Venice, Morocco, Ibiza, Monte Carlo and Malta20 percent at handover
Santorini4 percent on completion, then 30 percent across 24 months after handover

Where Venice stands today

Venice has not completed. The latest inspection report puts construction at 74.43 percent, and expected completion is 30 September 2027, exactly 24 months after its 29 September 2025 target.

Sales opened on 23 May 2022 and construction started on 28 December 2022, so the cluster was sold off plan roughly seven months before work began.

Source: Dubai Land Department project inspection records via PropertyMonitor. Checked 6 September 2026.

Back to Venice hub · Price list · Floor plans · Brochure

Venice FAQ

Is Venice at DAMAC Lagoons still available?
The Dubai Land Department registry records Venice as sold out, so developer stock is not available. It trades on the off plan resale market and the project has not completed.
How many homes are there in Venice?
425, all villas, in a single project with no phases. 274 are six bedroom and 151 are seven bedroom. Venice is the only DAMAC Lagoons cluster with no three, four or five bedroom homes.
When will Venice be handed over?
Venice has not completed. It is 74.43 percent built with expected completion on 30 September 2027, exactly 24 months after its 29 September 2025 target. Sales opened on 23 May 2022 and construction started on 28 December 2022.
What did Venice villas launch at?
Six bedroom villas launched from AED 4,570,000, a price that attaches to the smallest six bedroom unit at 4,066 sqft, or roughly AED 1,124 per sqft. Seven bedroom villas launched from AED 9,980,000 for the 10,672 sqft LV-D1E layout, or roughly AED 935 per sqft. The largest layouts carry no attributed launch price.
Why does Venice have the highest prices in DAMAC Lagoons?
Venice carries the highest all time registered median in the community at AED 7.35 million and the highest last 12 month rate at AED 1,358 per sqft. It is the only cluster built entirely of six and seven bedroom villas, with no smaller homes in its transaction book to pull the median down.
How big are Venice villas?
The registry records six bedroom villas from 4,066 to 24,752 sqft and seven bedroom villas from 10,672 to 17,590 sqft. Those spans cover more than one layout each. DAMAC's sheets confirm six layouts, from the 4,066.82 sqft LV-4E to the 24,752.58 sqft LV-1000E.